Gildemeister NEF 480 Retrofit

More
10 Mar 2021 21:10 #201716 by anfänger
The 8 degrees in the shop today were almost comfy. So I wired the Terminals in the console.

File Attachment:


And I straightened the bugger with some not to gentle blows with the hammer.

File Attachment:


And now the Panay sits well and I can start to figure out where to put the computer.
The following user(s) said Thank You: RotarySMP, J Green

Please Log in or Create an account to join the conversation.

More
12 Mar 2021 23:09 #202029 by anfänger
Installed the monitor and the computer. Also mounted the servo to determine the cable length.

File Attachment:


File Attachment:


Now all the wires in the console are finished and I closed the cable channel

File Attachment:


File Attachment:
The following user(s) said Thank You: tommylight

Please Log in or Create an account to join the conversation.

More
13 Mar 2021 00:21 #202037 by db1981
Hi,

sorry muss mal in Deutsch zwischenfragen...

Sind bei dir die Führungsflächen vom Schlitten mit Belag versehen, oder sind das einfach geschabte Flächen?
Bei mir ist da irgendein grauer Kunstoff drauf der fix und fertig aussieht, Habe jetzt keine Ahnung ob das so Original ist oder ob schon mal jemand daran rumgepfuscht hat....

Please Log in or Create an account to join the conversation.

More
13 Mar 2021 06:51 #202062 by anfänger
ich habe einen Liner and der vordern Führung. Ob das Original oder nachträglich kam kann ich nicht sagen. Aber auf den ersten Blick war bei mir alles Spielfrei, daher habe ich es erst mal so gelassen.

Please Log in or Create an account to join the conversation.

More
13 Mar 2021 22:34 #202159 by anfänger
Sind doch überall liner drunter hatte mir das heute noch mal genauer angesehen.

File Attachment:


Cleaning parts is never fun but most of them are done now. Just the two biggest housing parts I have left for later.
While cleaning some of them I wish I had opted for more wire work today
The following user(s) said Thank You: tommylight

Please Log in or Create an account to join the conversation.

More
14 Mar 2021 16:01 #202222 by anfänger
Fetched the hopefully fitting Tailstock today:

File Attachment:
Ohne Titel

It came with a center, so at least I have some cast Iron and a fitting center.

Please Log in or Create an account to join the conversation.

More
14 Mar 2021 19:09 #202248 by RotarySMP
Looks pretty beefy. Hope it fits your lathe well.
Mark

Please Log in or Create an account to join the conversation.

More
16 Mar 2021 17:50 - 17 Mar 2021 16:07 #202490 by anfänger
Sometimes when it sounds to cheap / good to be true, it simply isn't.
I found the fitting nipples for the oiler, and they arrived today. And I realized they are missing the pistons. So instead of the 50 quid fo the nipples I need the whole distributors, so it's 280 then and waiting again. Lead time is end of April.
Damn it

Patrick
Last edit: 17 Mar 2021 16:07 by anfänger.

Please Log in or Create an account to join the conversation.

More
19 Mar 2021 08:44 #202810 by anfänger
After this setbacks I moved on with connecting wires in detail the spindle stock

File Attachment:


Also some more wires to the VFD

File Attachment:


Next is turning my attention to the cabinet while waiting for the spare parts.

Thanks for listening

Patrick
The following user(s) said Thank You: RotarySMP, tommylight, db1981

Please Log in or Create an account to join the conversation.

More
19 Mar 2021 09:34 #202813 by tommylight

Thanks for listening.

We are not, we just read and look at the pictures! :)
Thanks for sharing.
The following user(s) said Thank You: RotarySMP